Lot-size for continuous production and process industry

A suitable lot-size for continuous production can be hard to come up with. Picture the situation of a mineral oils manufacturer that refines crude oil to 3 co-products. The planner wishes to control the process flow to align the production with demand (i.e. the refinery is not continuously refining at the same speed as it would in make-to-stock). Another requirement for ATP is that the production quantities are issued on a daily basis. Hence we want MRP to come up with weekly planned orders that are distributed on a daily basis. In abundance: 1 planned/process order per week, with equal quantities released per day.

 